Editorial composite showing a data-center server corridor, an electrical substation and a calculator on a financial report.

The AI build-out is costing hundreds of billions. Who is paying?

Written by Joseph Nordqvist

Published: 17:46, September 26, 2026

Artificial intelligence is often sold as software, but the industry is now spending on something much more physical: data centers, chips, power connections, cooling equipment and networks. The bills are being paid first by large technology companies, then by lenders, landlords and infrastructure investors. Over time, they must be paid back by customers.

Microsoft said capital expenditures reached $41 billion in its fiscal fourth quarter ended June 2026. Meta reported $31.08 billion of capital expenditure, including finance-lease principal payments, for the June quarter. Those two figures alone show why AI is becoming a capital-allocation story as much as a software story.

Neither number is a measure of AI spending alone. Both companies operate large cloud and digital businesses with wider infrastructure needs. But each company has made AI capacity central to its expansion plans.

Big Tech supplies the first dollars

The largest platforms can fund a substantial part of the build-out from their existing operations. Advertising, cloud computing, enterprise software and e-commerce produce cash that can be reinvested in servers and data centers.

Microsoft reported $55.4 billion in operating cash flow in its fiscal fourth quarter, alongside $19.6 billion in free cash flow after capital expenditures. It said roughly two-thirds of its $41 billion quarterly capex was for shorter-lived assets, primarily CPUs and GPUs. The remainder was for longer-lived assets, such as data-center infrastructure.

Meta generated $31.86 billion in operating cash flow in the June quarter, but its free cash flow after capital expenditure was $784 million. Its 2026 capital-expenditure outlook is $130 billion to $145 billion, including principal payments on finance leases.

These are not signs that either business lacks cash. They show how quickly a physical expansion can absorb cash even at companies with unusually profitable core operations.

Leases spread the construction bill

A technology company does not always buy a data center outright. It can sign a long-term agreement for capacity from a specialist developer. The developer raises the money for land, construction and equipment, then receives lease payments as the facility becomes available.

This changes who supplies the initial capital. It does not eliminate the commercial commitment. Microsoft, for example, said it recorded $5.6 billion of finance leases in its latest fiscal quarter, primarily for large data-center sites. The company also explained that a change to the estimated useful lives of its data centers would move more future leases from finance to operating leases, affecting how spending appears in its capex measure.

That accounting distinction matters to investors. A finance lease is generally included in a company’s capital-expenditure reporting, while an operating lease usually is not. Both can represent substantial future payments, so looking only at a single capex line can understate the scale of a company’s infrastructure commitments.

Chips and buildings have different economic lives

Data-center financing combines assets with very different replacement cycles. Land, buildings and grid connections can be useful for decades. Processors, memory and networking gear can lose their economic advantage much sooner as new generations arrive.

That makes the financing decision more complicated than a conventional property project. A lender may be comfortable with a building and a long customer contract, but the economics still depend on how long the installed computing equipment remains competitive and how reliably the customer uses the capacity.

Specialist data-center owners, private-credit funds and infrastructure investors can therefore participate alongside the technology companies. Their return depends on contracts, financing costs, power availability and the continued value of the computing capacity inside the building.

The grid is also part of the investment

Servers cannot produce a service without electricity. New AI capacity can require substations, transformers, transmission upgrades and new generation, costs that may sit with a utility, a developer, a data-center tenant or a combination of them.

The International Energy Agency projects that data-center electricity consumption could rise from about 485 terawatt-hours in 2025 to 950 terawatt-hours in 2030. A terawatt-hour measures electricity used over time. It is different from the maximum power a facility needs at a single moment.

Our earlier report on why data centers can wait years for a grid connection explains why a project with funding and servers can still be delayed by local transmission and substation constraints.

Customers are the final test

Capital expenditure, leases and external financing only begin the story. The lasting source of repayment is expected to be revenue from cloud capacity, AI software, usage-based services and products that use the new infrastructure.

Microsoft said demand for its cloud infrastructure continued to exceed available capacity in its fiscal fourth quarter. That is a company statement, not a guarantee that every new site will earn an attractive return. Demand can change, equipment prices can move and an expensive facility can take time to fill.

The central question for investors is return on capital. If customers continue to pay for enough computing and AI services, the build-out can support itself through revenue. If demand grows more slowly than capacity, companies may still face depreciation, lease payments and power costs from investments made years earlier.

The AI boom is therefore not being funded by a single payer. It is a chain: platform companies deploy cash, developers and lenders finance physical capacity, utilities invest in connections, and customers must eventually pay for services that make the system economic.

Microsoft’s figures are from its fiscal 2026 fourth-quarter earnings call. Meta’s figures are from its second-quarter 2026 results. The electricity projection is from the International Energy Agency’s Energy and AI analysis.

Joseph Nordqvist Avatar

Other News

Bank AI use was linked to a smaller share of small-business lending, Fed study finds

Sep 26, 2026

Iridium shareholders approve Rocket Lab takeover: what still has to happen

Sep 25, 2026

Akamai’s 11.6 billion dollar Anthropic deal ties cloud revenue to a 5.5 billion dollar buildout

Sep 25, 2026

Bentley completes 350 million pound Crewe investment as it unveils its first electric vehicle

Sep 25, 2026

Falling birth rates did not reduce total output in historical data, NBER study finds

Sep 25, 2026

Cheaper renewable power does not solve the capital problem for poorer countries

Sep 25, 2026

Facial payments may feel novel, but money worries can curb repeat use

Sep 24, 2026

Precision farming cuts water use while raising crop yields, study finds

Sep 24, 2026

EU allocates €505m to Lebanon for recovery, reforms and basic services

Sep 23, 2026

Alcoa raises $2.6bn in notes to fund South32 aluminium-assets deal

Sep 23, 2026

UK workplace health plan targets preventable exits from employment

Sep 23, 2026

IMF says Sri Lanka’s recovery is holding, but the next review is still unresolved

Sep 23, 2026

OECD sees global growth holding up after energy shock, but forecasts higher inflation

Sep 23, 2026

QAD and Redzone plan NVIDIA-powered AI for factory data and production planning

Sep 22, 2026

World Cup pitchside sponsorship raised a cross-border advertising problem

Sep 22, 2026

Hollywood’s biggest budgets still favour male-only teams, study finds

Sep 22, 2026

Why more companies are becoming their own insurers

Sep 22, 2026

EU publishes data-centre rating rules and opens consultation on minimum standards

Sep 21, 2026

ABB launches Infinitus DC portfolio for AI data centers, with first full sites expected in two to three years

Sep 21, 2026

Starbucks selects Chennai for a technology hub, with work set to move in-house over time

Sep 21, 2026