A reorder point is the stock level at which a business places a new order so that replenishment can arrive before stock runs out. It depends on expected demand during the wait for delivery and any extra stock the business chooses to hold.
Order too late and customers may face delays or find another supplier. Order too early and cash may sit in storage, alongside the risk of damage, expiry or products becoming obsolete.
Estimate demand while the order is on its way
Lead time is the interval between placing an order and receiving stock ready to sell or use. Include supplier processing, shipping, customs where relevant, and any inspection or preparation time after arrival.
Suppose a shop sells an average of 10 units a day and replenishment takes seven days. Expected demand during lead time is 70 units. If the shop chooses to hold 30 extra units as safety stock, the reorder point is 100 units: 70 plus 30.
That example assumes average demand and lead time are reasonable estimates, and that stock records are current. Safety stock is a buffer against uncertainty, not a guarantee against shortages. A larger buffer can reduce some stockout risk while increasing storage costs and cash tied up.
Use the stock position, not just the shelf count
A purchase already on its way may cover some future demand. Orders already promised to customers reduce what is available. A basic inventory position is stock on hand plus stock on order, minus unfilled customer commitments. Apply the same treatment consistently and investigate late or unreliable incoming orders separately.
When the inventory position reaches or falls below the reorder point, place the order under a continuous-review system. If stock is reviewed only once a week, the business also needs to cover demand until the next review, plus the subsequent lead time.
The reorder point says when to order. It does not say how many units to buy. Order quantity depends on storage, cash, supplier minimums, expiry dates and how often the business is prepared to reorder.
Allow for variation and check the records
Average demand can conceal busy days and seasonal peaks. Compare several relevant periods, identify unusual promotions or shortages, and look at actual delivery times. A seven-day average delivery time is less reassuring if some orders routinely take two weeks.
Choose a buffer appropriate to the product’s value and the consequences of a stockout. An inexpensive spare part that stops a production line may justify more protection than a seasonal item likely to expire. The Queensland government’s stock-control guidance discusses the cost of excess inventory, stocktaking and supplier lead times.
Check actual quantities against the system. Damage, returns, theft, reservation errors and incorrect receiving records can make a mathematically sound reorder point unreliable.
Review after a disruption or demand change
Recalculate when a supplier changes delivery terms, sales become seasonal, or a promotion alters demand. For goods sold in batches, consider minimum order quantities and how long the stock will remain usable.
Ask whether apparent backup suppliers depend on the same upstream source and whether they can deliver to specification. Our earlier coverage of supply-chain backup plans explains why an alternative supplier needs to be tested before a disruption.
Keep the assumptions beside the reorder point: daily demand, lead time, safety stock and review frequency. That record makes it easier to see which number needs to change when deliveries or sales no longer match the plan.